Question: 1 / 400

What should the contractor do once the work area is controlled and preparations have been made for disturbance?

Conduct a pre-abatement inspection

Notify local authorities

Remove all personnel from the area

Shut off, lock, and tag the electrical system

Once the work area is controlled and preparations for disturbance have been made, shutting off, locking, and tagging the electrical system is crucial. This step is important for safety, as it prevents accidental energization of electrical circuits during the asbestos removal or disturbance process. By ensuring that the electrical system is de-energized and securely locked out, the contractor minimizes the risk of electrical shock or other hazards that could arise during the abatement activities.

Locking and tagging the electrical systems is part of the Lockout/Tagout (LOTO) procedures, which are essential in any workplace where hazardous conditions may exist. This practice helps ensure that only authorized personnel can operate the equipment, maintaining a safe working environment for those involved in the asbestos abatement process.